In bored cast-in-place pile construction, the reinforcement cage is a core load-bearing component. Its fabrication quality, storage, lifting, positioning, and installation directly affect pile integrity, bearing capacity, and durability.
Based on extensive site experience and engineering practice, this article systematically summarizes the key technical points for reinforcement cage fabrication, storage, lifting, positioning, and anti-floating control, with a special focus on the application of mechanical rebar coupler connections, as promoted by GLUS.
1. Reinforcement Cage Fabrication
1.1 Dimensional Tolerances (Reference Standard)
According to the Specifications for Inspection and Evaluation of Highway Engineering Quality, the allowable fabrication tolerances for reinforcement cages are as follows:
| Item No. | Inspection Item | Allowable Deviation (mm) |
|---|---|---|
| 1 | Main bar spacing | ±20 |
| 2 | Stirrup or spiral spacing | ±10 |
| 3 | Cage diameter | ±5 |
| 4 | Cage length | ±10 |
1.2 Fabrication Method & Structural Reinforcement
Reinforcement cages shall be fabricated using the reinforcing ring forming method, with reinforcing rings arranged at intervals of approximately 2 m
Reinforcing rings shall be placed inside the main bars
Triangular internal braces are recommended to enhance rigidity
Main bars shall be spot-welded to the outer side of the reinforcing rings
Main bars must be perpendicular to reinforcing rings before tying stirrups
1.3 Welding Requirements for Main Bars
Main bar lap welding length: 10D (double-sided weld)
Due to incomplete weld formation at start and end points, it is recommended to:
Increase weld length by 10 mm
Welding joints shall be staggered, with spacing meeting code requirements
Reinforcing rings welded by butt welding show good performance and are recommended
Common quality risks:
Incomplete weld penetration
Burn damage to main bars due to excessive current or poor welding skills
GLUS Recommendation
Project teams should:
Organize welding skill assessments
Avoid high-current welding aimed only at speed
Assign clear responsibility to team leaders
2. Segmented Fabrication of Reinforcement Cages
Due to:
Large cage length and weight
Limited drilling rig mast height (typically ≤ 10 m)
Reinforcement cages are generally fabricated in segments.
Key requirements:
Segment length preferably matches standard rebar length
Segment length not less than 6 m
50% of joints shall be staggered
Rebar axes must be aligned on the same centerline
Bottom bars may be slightly flared (bell-shaped) to:
Prevent tremie pipe hooking
Reduce cage floating
3. Application of Mechanical Rebar Coupler Connections
3.1 Why Use Coupler Connections?
Traditional welding methods result in:
High rebar waste (10D lap length)
High labor and electricity costs
Quality variability
Mechanical coupler connections, such as parallel thread couplers, offer:
Stable and controllable connection quality
Reduced steel consumption
Faster installation during cage lowering
Field data shows that mechanical connections can reduce overall cost, depending on project conditions and skill level.
3.2 Key Quality Control Points for Coupler Connections
To ensure structural performance, attention must be paid to:
Threaded end processing
Rebar ends must be cut flat
Thread length must meet design requirements
Thread accuracy
Threads must not be too tight or too loose
Avoid over-cutting
Alignment control
Prevent one-sided engagement (one end more, one end less)
Mark rebars before assembly for consistency
Pre-assembly
Ensure sufficient site space for axial alignment
Number main bars to avoid mismatch
Improper alignment may lead to:
Reduced tensile strength
Failure to meet design requirements
4. Sonic Logging Tube (CSL Tube) Installation
4.1 Tube Specifications
Standard tube lengths: 9 m / 6 m / 3 m
Typical specification: Φ50 × 1.2 mm
4.2 Connection Methods
Recommended: Bolt-and-nut mechanical connection
Advantages:
Fast installation (over 5× faster than welding)
No special equipment required
No hot work on site
Reduced safety risks
Lower cost and material loss
Not affected by weather conditions
4.3 Installation Requirements
Tube length shall match cage length
Bottom tube shall extend 200–300 mm below cage bottom
Tubes must be filled with clean water
Seal with dedicated caps
Prevent blockage during concreting
5. Concrete Cover Control
Recommended Method: Concrete Roller Spacers
Spacer thickness = design concrete cover thickness
Arrangement:
4 spacers every 2 m, evenly distributed
Welded to main bars
Functions:
Ensure cage centering
Control concrete cover thickness
Prevent scratching of borehole wall
During lowering, install spacers progressively to avoid damage.
6. Storage of Reinforcement Cages
Store cages on level, dry ground
Place wooden blocks of equal height under reinforcing rings
Prevent contact with soil
Arrange segments in order
Attach labels indicating:
Segment number
Length
Protect from rain and corrosion
7. Lifting, Lowering & Positioning Control
7.1 Anti-Deformation Measures
Use temporary longitudinal stiffeners (e.g. wooden poles)
For long cages:
Bind two straight wooden poles inside the cage
7.2 Lifting Method (Two-Point Lifting)
First lifting point: lower part of the cage
Second lifting point: between midpoint and upper third
Lift sequence:
Lift lower point slightly
Lift both points together
Stop lower point once cage leaves ground
Continue lifting upper point until vertical
Do not drag the cage on the ground.
7.3 Cage Positioning
Slowly lower cage vertically
Avoid collision with borehole wall
Temporarily support cage at reinforcement rings during segment welding
Align upper and lower segments on the same axis
Final positioning:
Use surveyed pile top elevation to back-calculate cage position
Verify repeatedly before final welding
8. Prevention of Reinforcement Cage Floating During Concreting
Main Causes:
Tremie pipe hooking the cage during lifting
Upward concrete impact force during rapid pouring
Control Measures:
Control tremie pipe position:
Bottom ≥ 3 m below cage bottom
Not higher than 1 m above cage bottom
Slow down pouring rate when concrete reaches cage zone
Maximum recommended rise rate:
≤ 0.5 m/min (depending on pile diameter)
Adjust tremie embedment to increase concrete confinement
Control concrete slump and ensure continuous pouring
If cage floating is detected:
Immediately reduce pouring speed
Use “slow lift – quick drop” tremie operation to settle cage
9. Common Problems & Preventive Measures
Common issues include:
Cage floating
Cage falling during lowering
Misalignment
Deformation
Blocked CSL tubes
Key preventive actions:
Strengthen lifting points
Improve weld quality
Ensure proper lifting method
Use equal-length lifting slings
Never use folded two-rope lifting
Safety during lifting is critical. Accidents have occurred—safety first, always.
GLUS Engineering Value
At GLUS, we believe that reinforcement cages are not just steel assemblies—they are structural safety systems.
By combining:
Mechanical rebar coupler technology
Standardized fabrication control
On-site construction guidance
GLUS helps contractors:
Improve connection reliability
Reduce welding risks
Enhance construction efficiency
Achieve stable, inspectable quality in bored pile projects
Contact GLUS for rebar couplers, threading equipment, and integrated reinforcement connection solutions for foundation engineering.


